Mark Wilson I am the creator of TopXML. I am available for international and local (Australia) contracts. I am a Solution Architect/Business Analyst. I have worked in IT in several countries (NZ, Australia, South Africa, UK) building and training teams for government and very large non-governmental organizations. I am ex-Microsoft Consulting Services. I wrote the first book on Microsoft XML published in 2000 called XML Programming with VB and ASP. Most recently I have been building tools for the SEO industry. Ask me for a 37 point SEO health-checkup for your website.
Pad 34 (1)
Saturn-1 (1)
LC-34 dedicatation S-1 Stage ondock at KSCS-IV (dummy) Stage ondock at KSCS-IU ondock at KSCFull tank pressurization testLaunch
Dummy second (S-4) weighing 25,000 lbs and ballasted with 90,000 lbs
(11,000 gallons of water), Dummy third stage (S-5) weighing 3,000
lbs and ballasted with 100,000 lbs (12,000 gallons of water).
Research and Development of the S-1 launch vehicle. Test of
the S-1 stage propulsion and verify the structure and aerodynamics
of the vehicle.
October 27, 1961 10:06 a.m. Fully fueled and ready to go, the
Saturn weighed 925,000 lbs. The first stage was loaded with 600,000
lbs of propellant (kerosene fuel and liquid oxygen).
Prelaunch preparation began at 7:00am
on 10/26/61. Mechanical Office tasks included inspection of the high
pressure gas panel, cable masts, and fuel masts; ordnance installation;
and preparation of the holddown arms. The propellant team filled the
launch vehicle's tanks to the 10% level, using a slow, manual procedure
of approximately 750 liters per minute to check for leaks. A leak in
the fuel mast vacuum breaker was detected and easily repaired and at
2:30pm the launch team cleared the pad for the automatic "fast fill"
operation. Fuel flowed into the launch vehicle at 7570 liters per
minute reaching the 97% level in about 35min. The propellants team
then reverted to the "slow fill" procedure until the vehicle was
topped off at 103% of the required RP-1. The ten hour countdown
began at 11:00pm as LC-34 switched to the Cape's emergency
generating plant. Loading of the liquid oxygen started after 3:00am
(T-350). The Saturn LOX tanks were 10% filled to check for leaks in
the vehicle or in the 229 meter tranfer line, as well as precool the
line for the fast flow of super-cold LOX.
Two hours from the 9:00am scheduled liftoff, an unfavorable weather
report prompted launch officials to call a hold. The count resumed at
7:34am and the launch team rolled the service structure back to its
parking area. The propellants team configured the LOX facility for
fast fill (9500 liters per min) at T-100 and the blockhouse doors
were swung shut at T-65 min. Launch officials, concerned that a
patch of clouds over the Cape might obsure tracking cameras, called a
second hold at 9:14am. Within half an hour, the countdown resumed.
Launch came when the ground launch sequencer ordered the firing of
a solid propellant charge. The gases from the ignition accelerated
a turbine that in turn drove fuel and LOX pumps. Hydraulic valves
opened, allowing RP-1 and LOX into the combustion chambers, along with
a hypergolic fluid that ignited the mixture. The engines fired in pairs,
developing full thrust in 1.4 seconds. A final rough combustion check
was followed by ejection of LOX and RP-1 fill masts from the booster
base. The four hold-down arms released the rocket 3.97 seconds after
first ignition and SA-1 was airborne. [Moonport - A History of
Launch Facilities and Operations. Charles D. Benson and William B.
Faherty. NASA SP-4204 page 62].
137km xxx degrees(suborbital)0000 344km downrange
10/27/61. Impact in the Atlantic ocean 344km downrange
The only major difficulty that turned up with SA-1 was an unanticipated
degree of sloshing of propellants in the vehicle's tanks. Beginning with
vehicle SA-3, additional antislosh baffels were installed. SA-1 was
heavily instrumented with nearly 400 of SA-1's 510 telemetered readings
concerned with propulsion, temperature or pressure. Other measurements
included strain, vibration, flight mechanics, steering control,
stabilized platform, guidance, RF, voltage and current.
Pad 34 (2)
Saturn-1 (2)
S-1 Stage ondock at KSCS-IV (dummy) Stage ondock at KSCS-IU ondock at KSCLaunch
Water (95 tons), Dummy 2nd stage, Jupiter nose cone
April 25, 1962 09:00:34 a.m. EST.
xxx degrees(suborbital)0000
04/25/62
The first payload carried on SA-2 and SA-3 was called Project
Highwater, authorized by NASA's Office of Space Sciences. The
inert S-IV and S-V stages for these launches carried 109,000
liters (30,000 gallons) of ballast water for release in the upper
atmosphere. This was used to study the effects on radio
transmission and changes in local weather conditions. At an
altitude of 150km, explosive devices ruptured the S-IV and S-V
tanks and in just five seconds, ground observers saw the formation
of a hugh ice cloud estimated to be several kilometers in diameter.
Pad 34 (3)
Saturn-1 (3)
S-1 Stage ondock at KSCS-IV (dummy) Stage ondock at KSCS-IU ondock at KSCLaunch
Water (95 tons), Dummy 2nd stage, Jupiter nose cone
Launchxxx degrees(suborbital)0000
11/16/62. Impact in the Atlantic ocean
Pad 34 (4)
Saturn-1 (4)
S-1 Stage ondock at KSCS-IV Stage ondock at KSCS-IU ondock at KSCLaunch
Dummy second stage, Jupiter nose cone
The Saturn-1 booster S-1 stage consisted of a cluster of 8 H-1
engines. One of the appealing features of this configuration was
the added safety of providing for an "engine-out capability" where
other engines could burn longer than planned if an engine cutoff
early. On the SA-4 mission, a premature single engine cutoff
of one engine was programmed 100 seconds into the flight. This
experiment was successful. (NASA SP-4206 page 324).
March 28, 1963. 03:11:55 p.m. EST.
xxx degrees(suborbital)0000
03/28/63. Impact in the Atlantic ocean
WSMR Area #3 ()
Little Joe II
Launch
Boilerplate #6
Pad 37B (1)
Saturn-1 (5)
S-1 Stage ondock at KSCS-IV Stage ondock at KSCS-IU ondock at KSCLaunch
Live second stage, Instrument unit, ballasted Jupiter nose cone
January 29, 1964, 11:25:01 a.m. EST. Launch on 01/27/64 scrubbed
due to test flange left in S-1 stage liquid-oxygen (LOX) replenshment
line, preventing flow of LOX to vehicle; 73-minute hold on 01/29/64
due to interference in C-band radar and command destruct frequencies.
785km Apogee, 262km Perigeexxx degrees(orbital)0000
01/29/64.
WSMR ()
Little Joe II
Launch
Pad 37B (2)
Saturn-1 (6)
A-101 ()
S-1 Stage ondock at KSCS-IV Stage ondock at KSCS-IU ondock at KSCLaunch
Boilerplate 13 CSM, production LES, service module/launch vehicle adapter
Launch 227km Apogee, 182km Perigeexxx degrees0000
05/28/64
Pad 37B (3)
Saturn-1 (7)
A-102 ()
S-1 Stage ondock at KSCS-IV Stage ondock at KSCS-IU ondock at KSCLaunchLaunchxxx degrees0000
WSMR ()
Little Joe II
Launch
Pad 37B (4)
Saturn-1 (9)
A-103 ()
S-1 Stage ondock at KSCS-IV Stage ondock at KSCS-IU ondock at KSCLaunchLaunchxxx degrees0000
WSMR ()
Little Joe II
Launch
Pad 37B (5)
Saturn-1 (8)
A-104 ()
S-IV Stage ondock at KSCS-1 Stage ondock at KSCS-IU ondock at KSCLaunchLaunchxxx degrees0000
WSMR ()
Little Joe II
Launch
Pad 37B ()
Saturn-1 (10)
A-105 ()
S-1 Stage ondock at KSCS-IV Stage ondock at KSCS-IU ondock at KSCLaunchLaunchxxx degrees0000
Little Joe II
WSMR ()
Launch
Block I production model 002
Abort Qualification Program
NASA had hoped to finish the Little Joe II abort qualification program
by the end of 1965, but on 17 December the Flight Readiness Board refused
to accept the booster and canceled a launch set for the next day. A month
later, at 8:15 am on 1/20/66, the last Little Joe II headed toward an
altitude of 24 kilometers and a downrange distance of 14 kilometers. Then,
as designed, the launch vehicle started to tumble; the launch escape system
sensed trouble and fired its abort rocket, carrying the command module
away from impending disaster.
24kmx (suborbital) 14km
All went well, the launch, the test conditions, the telemetry, the
spacecraft and postflight analysis. The spacecraft windows picked up
too much soot from the tower jettison motor, but the structure
remained intact. Little Joe II was honorably retired, its basic
purpose - making sure the launch esc
Total Apollo time:
Seconds: 9115085
Days: 105.49866898148149
Name
Payload
Landing
Altitude
days
hours
minutes
seconds
SA-1 (1)
Dummy second (S-4) weighing 25,000 lbs and ballasted with 90,000 lbs
(11,000 gallons of water), Dummy third stage (S-5) weighing 3,000
lbs and ballasted with 100,000 lbs (12,000 gallons of water).
10/27/61. Impact in the Atlantic ocean 344km downrange
137km
0
0
0
0
SA-2 (2)
Water (95 tons), Dummy 2nd stage, Jupiter nose cone
04/25/62
0
0
0
0
SA-3 (3)
Water (95 tons), Dummy 2nd stage, Jupiter nose cone
11/16/62. Impact in the Atlantic ocean
0
0
0
0
SA-4 (4)
Dummy second stage, Jupiter nose cone
03/28/63. Impact in the Atlantic ocean
0
0
0
0
Pad-Abort-Test-1 (6)
Boilerplate #6
SA-5 (6)
Live second stage, Instrument unit, ballasted Jupiter nose cone
01/29/64.
785km Apogee, 262km Perigee
0
0
0
0
A-001 (7)
SA-6 (8)
Boilerplate 13 CSM, production LES, service module/launch vehicle adapter
05/28/64
227km Apogee, 182km Perigee
0
0
0
0
SA-7 (9)
0
0
0
0
A-002 (10)
SA-9 (11)
0
0
0
0
A-003 (12)
SA-8 (13)
0
0
0
0
Pad-Abort-Test-2 (14)
SA-10 (15)
0
0
0
0
A-004 (16)
Block I production model 002
24km
AS-201 (17)
CSM-009
February 26, 1966, 11:49 am EST. Splash down in Atlantic Ocean, 8472
kilometers downrange, Impact point 8.18 deg South, 11.15 deg West. Miss
distance 72 kilometers; Recovery by U.S.S. Boxer by 02:20pm EST.
Capsule Landing Weight: xxx,xxx lbs.
303 miles (488 kilometers)
0
0
36
59
AS-203 (18)
Nose Cone, LH2 in S-IVB
No Recovery
185km x 189km
0
0
0
0
AS-202 (19)
Spacecraft-011
August 25, 1966, 1:49pm EDT. Atlantic Ocean 16 deg 7min North by
168 deg 58min East. Miss distance 370 kilometers. Recovered by
U.S.S. Hornet at 11:17pm EDT 08/25/66. Landing Weight: xxx,xxx lbs.
1143 Km
0
0
33
28
Apollo-1 (20)
Spacecraft-012
Apollo-4 (20)
Spacecraft-017
November 9, 1967, 03:37 pm EST. Landing in Atlantic Ocean at
30deg 06min North and 172 deg 32min West. Missed pland impact point
by only 16km. Landing Weight: xxx,xxx lbs.
187km x 183km
0
8
36
59
Apollo-5 (21)
LM-1 and nose cone.
No recovery.
961km
0
0
0
0
Apollo-6 (22)
CM-020, SM-014, LTA-2R
April 4, 1968, 05:23pm EST. Exact landing point unknown, first
visual sighting at 27deg 40min North and 157deg 59min West. Capsule
recovered by U.S.S. Okinawa and on board at 10:55 p.m. EST.
367km
0
10
22
59
Apollo-7 (23)
CSM-101
The CSM's service propulsion system, which had to fire the CSM into and
out of Moon orbit, worked perfectly during eight burns lasting from half
a second to 67.6 seconds. Apollo's flotation bags had their first try-out
when the spacecraft, a "lousy boat," splashed down in the Atlantic southeast
of Bermuda, less than two kilometers from the planned impact point. Landing
location was 27deg 32min North and 64deg 04min West. The module turned
upside down; when inflated, the brightly colored bags flipped it aright. The
tired, but happy, voyagers were picked up by helicopter and deposited on the
deck of the U.S.S. Essex by 08:20am EDT. Spacecraft aboard ship at 09:03am.
140 x 183 miles
10
20
0
0
Apollo-8 (24)
CSM-103
December 27, 1968; 10:52 am EST; Landing point 8deg 7.5min North and
165deg 1.2min West. Miss distance was 2.5km; Splashdown time, December
27, 1968 at 10:52 a.m. EST; MET: 147:00:42. Crew on board U.S.S
Yorktown at 12:20 p.m. EST; Spacecraft aboard ship at 01:20 p.m.
190km x 180km
6
3
0
42
Apollo-9 (25)
CSM-104 (Gumdrop) and LM-3 (Spider)
March 13, 1969 at 12:01 p.m. EST; Landing point 23deg 12.5min North
and 67deg 56min West (Atlantic Ocean). Miss distance 4.8 kilometers. Crew
on board U.S.S Guadalcanal at 12:45pm EST; Spacecraft aboard ship at 02:13pm.
192km x 190km
10
01
0
0
Apollo-10 (26)
CSM-106 (Charlie Brown) and LM-4 (Snoopy)
May 26, 1969; 12:52am EDT. Landing point 15deg 2min South by
164deg 39min West; Miss distance not available. Crew on board
U.S.S. Princeton at 01:31 p.m. EDT; spacecraft aboard ship at 02:28 p.m.
190km x 184km
08
0
3
23
Apollo-11 (27)
CSM-107 (Columbia) and LM-5 (Eagle)
July 24, 1969; 12:50 p.m. EDT. Splashdown area 13deg 19min North and
169deg 9 min West; Splashdown at 195:18:35 MET. Crew on board
U.S.S Hornet at 01:53 p.m. EDT; spacecraft aboard ship at 03:50pm.
186km x 183km
08
03
18
35
Apollo-12 (28)
Yankee Clipper (CM-108) and Intrepid (LM-6)
November 24, 1969
xxx miles
10
04
36
0
Apollo-13 (29)
Odyssey (CM-109) and Aquarius (LM-7)
April 17, 1970
xxx miles
05
22
54
0
Apollo-14 (30)
Apollo 14 Kitty Hawk (CM-110) and Antares (LM-8)
February 09, 1971
xxx miles
09
0
0
0
Apollo-15 (31)
Apollo 15 Endeavor (CM-112) and Falcon (LM-10)
August 07, 1971
xxx miles
12
17
12
0
Apollo-16 (32)
Apollo 16 Casper (CM-113) and Orion (LM-11)
April 27, 1972
xxx miles
11
01
51
0
Apollo-17 (33)
Apollo 17 America (CM-114) and Challenger (LM-12)
December 19, 1972
xxx miles
12
13
52
0
Total Apollo time:
Seconds: 9115085
Days: 105.49866898148149
Name
Payload
Landing
Altitude
days
hours
minutes
seconds
SA-1 (1)
Dummy second (S-4) weighing 25,000 lbs and ballasted with 90,000 lbs
(11,000 gallons of water), Dummy third stage (S-5) weighing 3,000
lbs and ballasted with 100,000 lbs (12,000 gallons of water).
10/27/61. Impact in the Atlantic ocean 344km downrange
137km
0
0
0
0
SA-2 (2)
Water (95 tons), Dummy 2nd stage, Jupiter nose cone
04/25/62
0
0
0
0
SA-3 (3)
Water (95 tons), Dummy 2nd stage, Jupiter nose cone
11/16/62. Impact in the Atlantic ocean
0
0
0
0
SA-4 (4)
Dummy second stage, Jupiter nose cone
03/28/63. Impact in the Atlantic ocean
0
0
0
0
Pad-Abort-Test-1 (6)
Boilerplate #6
SA-5 (6)
Live second stage, Instrument unit, ballasted Jupiter nose cone
01/29/64.
785km Apogee, 262km Perigee
0
0
0
0
A-001 (7)
SA-6 (8)
Boilerplate 13 CSM, production LES, service module/launch vehicle adapter
05/28/64
227km Apogee, 182km Perigee
0
0
0
0
SA-7 (9)
0
0
0
0
A-002 (10)
SA-9 (11)
0
0
0
0
A-003 (12)
SA-8 (13)
0
0
0
0
Pad-Abort-Test-2 (14)
SA-10 (15)
0
0
0
0
A-004 (16)
Block I production model 002
24km
AS-201 (17)
CSM-009
February 26, 1966, 11:49 am EST. Splash down in Atlantic Ocean, 8472
kilometers downrange, Impact point 8.18 deg South, 11.15 deg West. Miss
distance 72 kilometers; Recovery by U.S.S. Boxer by 02:20pm EST.
Capsule Landing Weight: xxx,xxx lbs.
303 miles (488 kilometers)
0
0
36
59
AS-203 (18)
Nose Cone, LH2 in S-IVB
No Recovery
185km x 189km
0
0
0
0
AS-202 (19)
Spacecraft-011
August 25, 1966, 1:49pm EDT. Atlantic Ocean 16 deg 7min North by
168 deg 58min East. Miss distance 370 kilometers. Recovered by
U.S.S. Hornet at 11:17pm EDT 08/25/66. Landing Weight: xxx,xxx lbs.
1143 Km
0
0
33
28
Apollo-1 (20)
Spacecraft-012
Apollo-4 (20)
Spacecraft-017
November 9, 1967, 03:37 pm EST. Landing in Atlantic Ocean at
30deg 06min North and 172 deg 32min West. Missed pland impact point
by only 16km. Landing Weight: xxx,xxx lbs.
187km x 183km
0
8
36
59
Apollo-5 (21)
LM-1 and nose cone.
No recovery.
961km
0
0
0
0
Apollo-6 (22)
CM-020, SM-014, LTA-2R
April 4, 1968, 05:23pm EST. Exact landing point unknown, first
visual sighting at 27deg 40min North and 157deg 59min West. Capsule
recovered by U.S.S. Okinawa and on board at 10:55 p.m. EST.
367km
0
10
22
59
Apollo-7 (23)
CSM-101
The CSM's service propulsion system, which had to fire the CSM into and
out of Moon orbit, worked perfectly during eight burns lasting from half
a second to 67.6 seconds. Apollo's flotation bags had their first try-out
when the spacecraft, a "lousy boat," splashed down in the Atlantic southeast
of Bermuda, less than two kilometers from the planned impact point. Landing
location was 27deg 32min North and 64deg 04min West. The module turned
upside down; when inflated, the brightly colored bags flipped it aright. The
tired, but happy, voyagers were picked up by helicopter and deposited on the
deck of the U.S.S. Essex by 08:20am EDT. Spacecraft aboard ship at 09:03am.
140 x 183 miles
10
20
0
0
Apollo-8 (24)
CSM-103
December 27, 1968; 10:52 am EST; Landing point 8deg 7.5min North and
165deg 1.2min West. Miss distance was 2.5km; Splashdown time, December
27, 1968 at 10:52 a.m. EST; MET: 147:00:42. Crew on board U.S.S
Yorktown at 12:20 p.m. EST; Spacecraft aboard ship at 01:20 p.m.
190km x 180km
6
3
0
42
Apollo-9 (25)
CSM-104 (Gumdrop) and LM-3 (Spider)
March 13, 1969 at 12:01 p.m. EST; Landing point 23deg 12.5min North
and 67deg 56min West (Atlantic Ocean). Miss distance 4.8 kilometers. Crew
on board U.S.S Guadalcanal at 12:45pm EST; Spacecraft aboard ship at 02:13pm.
192km x 190km
10
01
0
0
Apollo-10 (26)
CSM-106 (Charlie Brown) and LM-4 (Snoopy)
May 26, 1969; 12:52am EDT. Landing point 15deg 2min South by
164deg 39min West; Miss distance not available. Crew on board
U.S.S. Princeton at 01:31 p.m. EDT; spacecraft aboard ship at 02:28 p.m.
190km x 184km
08
0
3
23
Apollo-11 (27)
CSM-107 (Columbia) and LM-5 (Eagle)
July 24, 1969; 12:50 p.m. EDT. Splashdown area 13deg 19min North and
169deg 9 min West; Splashdown at 195:18:35 MET. Crew on board
U.S.S Hornet at 01:53 p.m. EDT; spacecraft aboard ship at 03:50pm.
186km x 183km
08
03
18
35
Apollo-12 (28)
Yankee Clipper (CM-108) and Intrepid (LM-6)
November 24, 1969
xxx miles
10
04
36
0
Apollo-13 (29)
Odyssey (CM-109) and Aquarius (LM-7)
April 17, 1970
xxx miles
05
22
54
0
Apollo-14 (30)
Apollo 14 Kitty Hawk (CM-110) and Antares (LM-8)
February 09, 1971
xxx miles
09
0
0
0
Apollo-15 (31)
Apollo 15 Endeavor (CM-112) and Falcon (LM-10)
August 07, 1971
xxx miles
12
17
12
0
Apollo-16 (32)
Apollo 16 Casper (CM-113) and Orion (LM-11)
April 27, 1972
xxx miles
11
01
51
0
Apollo-17 (33)
Apollo 17 America (CM-114) and Challenger (LM-12)
December 19, 1972
xxx miles
12
13
52
0
Total Apollo time:
Seconds: 9115085
Days: 105.498669
Name
Payload
Landing
Altitude
days
hours
minutes
seconds
SA-1 (1)
Dummy second (S-4) weighing 25,000 lbs and ballasted with 90,000 lbs
(11,000 gallons of water), Dummy third stage (S-5) weighing 3,000
lbs and ballasted with 100,000 lbs (12,000 gallons of water).
10/27/61. Impact in the Atlantic ocean 344km downrange
137km
0
0
0
0
SA-2 (2)
Water (95 tons), Dummy 2nd stage, Jupiter nose cone
04/25/62
0
0
0
0
SA-3 (3)
Water (95 tons), Dummy 2nd stage, Jupiter nose cone
11/16/62. Impact in the Atlantic ocean
0
0
0
0
SA-4 (4)
Dummy second stage, Jupiter nose cone
03/28/63. Impact in the Atlantic ocean
0
0
0
0
Pad-Abort-Test-1 (6)
Boilerplate #6
SA-5 (6)
Live second stage, Instrument unit, ballasted Jupiter nose cone
01/29/64.
785km Apogee, 262km Perigee
0
0
0
0
A-001 (7)
SA-6 (8)
Boilerplate 13 CSM, production LES, service module/launch vehicle adapter
05/28/64
227km Apogee, 182km Perigee
0
0
0
0
SA-7 (9)
0
0
0
0
A-002 (10)
SA-9 (11)
0
0
0
0
A-003 (12)
SA-8 (13)
0
0
0
0
Pad-Abort-Test-2 (14)
SA-10 (15)
0
0
0
0
A-004 (16)
Block I production model 002
24km
AS-201 (17)
CSM-009
February 26, 1966, 11:49 am EST. Splash down in Atlantic Ocean, 8472
kilometers downrange, Impact point 8.18 deg South, 11.15 deg West. Miss
distance 72 kilometers; Recovery by U.S.S. Boxer by 02:20pm EST.
Capsule Landing Weight: xxx,xxx lbs.
303 miles (488 kilometers)
0
0
36
59
AS-203 (18)
Nose Cone, LH2 in S-IVB
No Recovery
185km x 189km
0
0
0
0
AS-202 (19)
Spacecraft-011
August 25, 1966, 1:49pm EDT. Atlantic Ocean 16 deg 7min North by
168 deg 58min East. Miss distance 370 kilometers. Recovered by
U.S.S. Hornet at 11:17pm EDT 08/25/66. Landing Weight: xxx,xxx lbs.
1143 Km
0
0
33
28
Apollo-1 (20)
Spacecraft-012
Apollo-4 (20)
Spacecraft-017
November 9, 1967, 03:37 pm EST. Landing in Atlantic Ocean at
30deg 06min North and 172 deg 32min West. Missed pland impact point
by only 16km. Landing Weight: xxx,xxx lbs.
187km x 183km
0
8
36
59
Apollo-5 (21)
LM-1 and nose cone.
No recovery.
961km
0
0
0
0
Apollo-6 (22)
CM-020, SM-014, LTA-2R
April 4, 1968, 05:23pm EST. Exact landing point unknown, first
visual sighting at 27deg 40min North and 157deg 59min West. Capsule
recovered by U.S.S. Okinawa and on board at 10:55 p.m. EST.
367km
0
10
22
59
Apollo-7 (23)
CSM-101
The CSM's service propulsion system, which had to fire the CSM into and
out of Moon orbit, worked perfectly during eight burns lasting from half
a second to 67.6 seconds. Apollo's flotation bags had their first try-out
when the spacecraft, a "lousy boat," splashed down in the Atlantic southeast
of Bermuda, less than two kilometers from the planned impact point. Landing
location was 27deg 32min North and 64deg 04min West. The module turned
upside down; when inflated, the brightly colored bags flipped it aright. The
tired, but happy, voyagers were picked up by helicopter and deposited on the
deck of the U.S.S. Essex by 08:20am EDT. Spacecraft aboard ship at 09:03am.
140 x 183 miles
10
20
0
0
Apollo-8 (24)
CSM-103
December 27, 1968; 10:52 am EST; Landing point 8deg 7.5min North and
165deg 1.2min West. Miss distance was 2.5km; Splashdown time, December
27, 1968 at 10:52 a.m. EST; MET: 147:00:42. Crew on board U.S.S
Yorktown at 12:20 p.m. EST; Spacecraft aboard ship at 01:20 p.m.
190km x 180km
6
3
0
42
Apollo-9 (25)
CSM-104 (Gumdrop) and LM-3 (Spider)
March 13, 1969 at 12:01 p.m. EST; Landing point 23deg 12.5min North
and 67deg 56min West (Atlantic Ocean). Miss distance 4.8 kilometers. Crew
on board U.S.S Guadalcanal at 12:45pm EST; Spacecraft aboard ship at 02:13pm.
192km x 190km
10
01
0
0
Apollo-10 (26)
CSM-106 (Charlie Brown) and LM-4 (Snoopy)
May 26, 1969; 12:52am EDT. Landing point 15deg 2min South by
164deg 39min West; Miss distance not available. Crew on board
U.S.S. Princeton at 01:31 p.m. EDT; spacecraft aboard ship at 02:28 p.m.
190km x 184km
08
0
3
23
Apollo-11 (27)
CSM-107 (Columbia) and LM-5 (Eagle)
July 24, 1969; 12:50 p.m. EDT. Splashdown area 13deg 19min North and
169deg 9 min West; Splashdown at 195:18:35 MET. Crew on board
U.S.S Hornet at 01:53 p.m. EDT; spacecraft aboard ship at 03:50pm.